United Kingdom
PAS-128 survey at a clean water treatment works
Clean water treatment works
The challenge
The site had to remain fully operational throughout an expansion project, so every buried utility needed identifying without interrupting treatment operations.
Our solution
We combined ground penetrating radar with electromagnetic detection, paired with a topographical survey to record utility positions accurately against the wider site.
The outcome
Every buried utility on site was located while the works continued to operate without interruption throughout the expansion project.
“With the site remaining active throughout the expansion works, it was imperative that we worked together as a team and used every effort possible to locate every buried utility.”
Services used: PAS-128 survey, Ground penetrating radar, Topographical survey
Discuss a similar project